245 1 0 _aFoundation investigation for the proposed field force camp in Kroh, Perak
_nno. E(F)1/1976
_cShu Yeoh Khoon & Chow Weng Sum
260 _c1976
300 _a17 p.
_bill.,photos
_c30 cm
520 _aIn this respect the nature and volume of bedrock that need to be removed is critical to the overall cost estimate for the project and extensive programme of seismic survey was undertake to provide the necessary date for evaluation
650 0 _aGeology investigation